Two approvals to think about
A shed on a rural or rural residential lot can need two things:
- Planning approval (development approval). Many shires let you skip this if the shed meets their outbuilding policy. If it doesn't, you apply and explain why.
- A building permit. Most sheds over 10 m² or 2.4 m high need one, rural or not. Genuine farm buildings are treated as a separate building type, but you usually still need a permit. Ask your shire.
What rural shed policies usually cover
Each shire writes its own rules, so councils vary. The Shire of Northam's policy for its Rural Residential, Rural Smallholding and Rural zones is a good example of what to expect.
| Lot size | Biggest single shed | All sheds combined |
|---|---|---|
| Under 2 ha | 200 m² | 200 m² |
| 2 to 5 ha | 250 m² | 250 m² |
| 5 to 15 ha | 300 m² | 500 m² |
| 15 to 40 ha | 400 m² | 750 m² |
| Over 40 ha | 1,000 m² | Case by case |
Northam also sets wall heights from 4 m (within 20 m of a boundary) up to 5 m (50 m or more away). Sheds must sit inside any building envelope and not between the house and the road on Rural Residential lots.
Common rural rules to check
- Shed before a house. Many shires won't approve a shed on a vacant rural residential lot unless the house is approved first or at the same time. Northam also asks for a $20,000 bank guarantee.
- Toilets and showers. Often only allowed if there's already a house on the lot.
- Living in it. Not allowed. A shed is not a house.
- Second-hand materials and colours. Northam needs planning approval for second-hand materials and asks for pre-painted wall sheeting in its rural residential zones.
- Farm sheds. On Rural-zoned land, Northam doesn't apply the size limits to sheds the Shire agrees are needed for farming.
- Bushfire. Rural lots are often bushfire prone. Put the shed in a cleared area and build to the bushfire standard where needed.
Steps
- Find your lot's zone and any building envelope on your shire's map.
- Read your shire's outbuilding policy for that zone.
- If the shed meets it, apply for the building permit. If not, apply for planning approval first.
- Lodge the permit with a site plan, shed plans and engineering.
See the shed size checker, sheds in bushfire areas and planning vs building permit.