Two different approvals
| Planning (development) approval | Building permit | |
|---|---|---|
| What it checks | Where the shed goes and how big it is: setbacks, size, height, street look | How it's built: structure, wind, footings, fire separation |
| Rules it uses | The R-Codes, your council's planning scheme and policies | The Building Act and the National Construction Code |
| Needed for a shed? | Only if it doesn't meet the standard rules | Yes, unless it's small (see below) |
| Form | Application for Development Approval | BA1 (certified) or BA2 (uncertified) |
| Usual timeframe | Up to 60 days (90 if neighbours are asked) | 10 business days (BA1) or 25 (BA2) |
When a shed needs a building permit
Most do. Perth councils usually exempt a shed that is freestanding, no bigger than 10 m² and no taller than 2.4 m. Anything bigger needs a building permit. A small exempt shed must still be built properly.
When a shed also needs planning approval
Under the standard R-Codes rules for outbuildings, a backyard shed on a house lot usually doesn't need planning approval if it:
- is no bigger than 60 m² or 10% of the lot (whichever is less), counting all your outbuildings together,
- has walls no higher than 2.4 m and a ridge no higher than 4.2 m,
- isn't in the front setback, and
- meets the side and rear setbacks and leaves enough open space.
Go over any of those and you'll usually need planning approval first, then the building permit. Councils vary. For example, the City of Bayswater's Residential Development Policy (September 2026) allows outbuilding walls up to 3.0 m. Heritage areas, rural zones and special estates can have their own rules too.
Which comes first?
If you need both, get planning approval first. The building permit has to match what was approved, and councils won't usually issue it until planning conditions are met.
Check your shed with the shed size checker, read how to get a shed permit, or see how close a shed can be to the fence.